|
Return to Main Menu |
Currents
To MUSC Employees:
In the Feb. 10 Currents newsletter I mentioned that our Disproportionate
Share Funding (DSH) was in jeopardy. DSH match funding over the years has
been made available to MUSC by the U.S. Department of Health and Human
Services’ Center for Medicaid and Medicare Services (CMS) to help fund
care for Medicaid and indigent patients. These funds are channeled through
the State Department of Health and Human Services to MUSC.
Recently, a number of key elected officials representing South Carolina
met with the CMS leadership. It was agreed that there would be no
change in the South Carolina DSH funding for Fiscal Year 2004 and we are
hopeful there will be no change for Fiscal Year 2005. However, it was not
clarified whether the Medical Center’s funding for this year would be at
the FY 2003 level of approximately $36 million or at our budgeted level
of $40 million for FY 2004. We are very pleased with this most recent development
and we are hopeful of achieving “full” funding for FY 2004, but this remains
unclear.
On another matter, recently I heard a presentation by Nathan S. Kaufman
of the Superior Consultant Company Inc. The presentation focused upon characteristics
for peak performing hospitals including “Critical Performance Indicators.”
Remaining financially strong was highlighted as a key to success. It was
emphasized that given all of the unexpected costs and other budgetary challenges,
top performing hospitals must achieve an operating margin of 5 percent
or more.
Currently we are struggling to achieve a 3 percent margin. As we move
forward, we need everyone’s efforts devoted to efficient operations and
achieving cost savings while providing high quality and compassionate care.
Thank you very much.
W. Stuart Smith
Vice President for Clinical Operations and
Executive Director, MUSC Medical Center
Update on hospital replacement project
Facilities and Capital Improvements administrator Hal Currey presented
a progress update of MUSC’s hospital replacement project to those gathered
for the weekly hospital communications meeting Tuesday.
With most items on Currey’s task list labeled “on schedule,” he emphasized
the “next steps” and their estimated completion times, and he concluded
with unmitigated praise for the hard work and skill demonstrated by those
responsible for initiating the project and keeping its progress up-to-date.
Negotiations with the City of Charleston have accomplished most of what
the project requires, including height and setback issues, an understanding
about traffic and drainage issues, and support for a storm water lift station.
Work continues on the design of long-term traffic improvements, Currey
said.
Other “next steps” include:
-
Veterans Affairs: Get an agreed to 75-year lease of Doughty Street signed
and the associated easements approved
-
Financial Feasibility: With the feasibility study completed, accepted by
the board and submitted to the federal Department of Housing and Urban
Development, an update to include the construction cost of the central
energy plant is being prepared
-
The project’s certificate of need from the S.C. Department of Health and
Environmental Control has been approved and received, but an exemption
for a central energy plant is being prepared
-
As for HUD 242 financing, the project will be referred to committee after
submission of a guaranteed maximum price with a target loan closing set
for early June
-
Property acquisition from MUSC to the Hospital Authority has been completed.
Negotiated purchases of a county garage to MUSC and McClennan-Banks Court
to the Hospital Authority await completion
-
Some highway and traffic issues await a secure approval of the appropriation
of $63 million in a federal transportation bill.
Closer to home for those immediately affected by Phase 1 of the hospital
replacement project is the relocation of activities in that portion of
the Student Wellness Center slated for demolition. “We have identified
space for the impacted programs,” Currey said, “and we expect to have them
relocated by March 19.” Once that is accomplished, the next step will be
to begin demolishing the wellness center’s south wings.
Currey said he was especially pleased with the hearty approval the Board
of Architectural Review gave to the final building design when it was presented
Dec. 15. Once a guaranteed maximum price is secured from the construction
manager, site work will begin.
With demolition of the old McClennan-Banks hospital building completed,
a few critical tasks remain:
-
The guaranteed maximum price submitted to HUD—end of March;
-
Receipt of a commitment by HUD to insure the project loan—early June;
-
Closing on the HUD loan—early August;
-
Close Doughty Street—July 1 to Aug. 30;
-
New hospital construction begins—July 2 to Sept. 1;
-
Take occupancy of the new hospital —spring 2007.
The following is a list of the new components to be included in Phase 1
of the Replacement Hospital Project:
-
156 beds for cardiovascular and digestive disease services (includes 32
ICU beds)
-
Nine operating rooms including one equipped with fixed equipment for vascular
surgery
-
Three electrophysiology labs, four interventional/diagnostic catheter labs,
two interventional radiology labs (plus a third IR lab equipped with computerized
tomography (CT))
-
Nine endoscopy suites and two motility rooms
-
Outpatient clinics (to accommodate approximately 70,000 visits) and associated
faculty offices.
-
Specialize chest pain center (includes observation beds)
-
Imaging capacity to include two diagnostic CTs, one interventional CT,
one diagnostic MRI (magnetic resonance imaging), three nuclear cameras,
three RF rooms, and space for a new modality to serve the chest pain center
and outpatient cardio-diagnostics.
Currey concluded by saying, “I’d like to thank each of you who have made
the Phase 1 project move at an incredible rate. Just to jog your memory,
in early December 2002, the Charleston City Planning Commission recommended
approval of the new hospital overlay district. On Jan. 20, a little more
than 13 months later, we have a guaranteed maximum price.”
He listed nearly 25 critical tasks that were performed to advance the
project along to its present stage. Currey named Sandra Wade, Deborah Blackwell,
Chris Malanuk, Kim Duckworth, Boyd Wood, Stephanie Davis, and Kim Horan.
“The individual and team effort to make all of this happen is extraordinary.
It is absolutely proof positive of the fact that intelligence, a sense
of good will, the ability and willingness to work hard, patience and perseverance
really pay off,” he said.
Announcement
Technology manager Dan Altman gave an update of progress on the equipment
tracking system, which is scheduled to be installed in the next week. He
explained that the installation involves the use of new containment units,
required when it is necessary to enter and run wires in overhead areas
of the hospital.
“The installation will begin on the tenth floor of the main hospital
and affect the main hospital and the Children’s Hospital,” he said.
For information, contact Robert Tritt of Biomedical Engineering at 792-3984,
pager 12342. Altman can be reached at 792-6426, pager 11003.
Children's
Hospital Administrator John Sanders greets Charleston Lowgators mascot
Al the Lowgator at MUSC Family Night Feb. 28. For each ticket purchased
by an MUSC/MUHA/UMA/CFC employee or student, the Lowgators donated $1 to
the Children's Hospital. Sanders was presented a representative check made
out for $265. An actual donation of $276 was made to the Children's Hospital
from the ticket sales. An additional $100, it was later revealed, came
from an anonymous donor who was grateful for not having to take part in
the halftime tricycle relay race entertainment (that Sanders' team won,
by the way).
Friday, March 12, 2004
|